ETCS Level 2 for the Gotthard Base Tunnel

Client
AlpTransit Gotthard AG, Lucerne
Period
2009
2017
Fields of activity
Infrastructure;Rail infrastructure;Mobility and traffic;Rail systems
Delivered services
Supervising the contractor
Assistance to the Client (ATG)
Technical support
Project management
Verification of the RAMS process
Cost controlling
Specifications
Two separated running tunnels: 57 km
Train speed: 80-250 km/h
Headway: 3 min
Train control system: ETCS level 2
RBC with GSM-R interface: 3
Interlockings: 4
Balises: 370
Central Control System: 1

Project description

Assistance of detailed design, realisation and commissioning of the new train control and signalling system for the Gotthard base tunnel on behalf of AlpTransit Gotthard AG.

The project is carried out by a consortium under the lead of Emch+Berger AG Bern. The works includes all signalling related systems on an ERTMS-basis in the perimeter of the project such as control and communication system, interlocking, ETCS/RBC and is embedded over special interfaces into other neighbouring signalling systems (conventional signalling systems).