Back to overview

New office building for Roche Group IT

Roche is planning to bring together approx. 1'300 employees of its in-house IT department on its site in Kaiseraugst. 4 new buildings will be built in a very short space of time. The construction work began in the 1st quarter of 2015. The goal of this “fast track project” is to hand over the first two buildings ready for use at the end of 2016. Emch+Berger AG Gesamtplanung Hochbau Basel will be in charge of the project after the conceptual design phase as general planner.
Place

Kaiseraugst

Client

F. Hoffmann-La Roche AG

Builder

F. Hoffmann-La Roche AG

Period
2013
2017
Project number
GP.N.14060
Fields of activity
General planning
Delivered services

General planner overall project management basic design phase (completed)

General planner overall project management current detail design phase

Specifications

Floor space: 50'770 m2

4 buildings with atriums

work stations: 1'550

Two cafeteria on ground floor

aluminium panel façade with projecting precast concrete façade